hello@torquemanagementservices.com

Success Stories

  • Home
  • Success Stories

Success Story 1 :-

A Leading Auto Electrical Unit

Project was all about creation of model Single Part Flow Production Assembly Line.
Time period: 6-months.
Objectives were:
  1. Improvement of Productivity by 30%
  2. Reduction of PPM level by 50% (Quality)
  3. Reduction in inventories
Key activities taken up were:
  1. Revamping of cellular line
  2. Implementation of 2-Bin System
  3. Cycle Time improvements thru’ Video Studies
  4. Hourly feeding of materials deploying Water Spider
  5. Line balancing and employing Rabbit Chase concept
  6. Avoiding wastes in material feeding by adopting direct feeding instead of multiple material handling
  7. Reorganizing Stores with better Visual Control
  8. Improving overall 5S

Success Story 2 :-

A Chassis Manufacturing Shop of a leading Automobile Company

Project was about inventing values in Chassis Manufacturing process through elimination of wastes by application of Lean Principles.
Duration: 9-Months
Key objectives were:
  1. Improving Ergonomics (EEI)
  2. Improvement in Quality level from 191 DMP to 100 DMP
  3. Improvement of 5S up-to 70% or more
  4. Reduction of WIP’s
  5. Organizing Warehouses in such a manner that FIFO is followed as system & inventories can be better managed
  6. Improvement in Productivity by 20-30%
  7. Safe work Environment eliminating Accidents & Incidents
Basic theme considered was to declare a war against :
  1. Too Messy
  2. Too Much
  3. Too Heavy
  4. Poor Visual Control
Typical results achieved were:


  1. 5S Level improved from 35% to 78% winning Second Position in 5S Excellence Award by AOTS-ABK
  2. Quality level improved to below 100 DMP level
  3. WIP reduced from 8-hours to 2-hours
  4. Savings in space over 20%
  5. Better utilization of operators due to streamlined material flow and deployment of Water Spiders
  6. Avoidance of Excess / Non-Moving Stocks
  7. Excellent Visual Control deploying better / smaller trolleys, bins etc

Success Story 3 :-

A Lighting Unit

Project was deployment of Lean concept for increased cost competitiveness.
Project Duration: 6 Months
Results achieved were:
  1. Clean & Tidy Shop
  2. Safer Work Environment
  3. 16-22% reduction in direct manpower in 2-different shops
  4. 20% reduction in inventories
  5. 15% savings in space
Typical activities taken up were:
  1. Relaying out of Lines
  2. Resolving critical issues concerning Quality and Production
  3. Implementation of Standing work culture
  4. Overhauling of Stores
  5. Direct material feeding in between machines
  6. Better utilization of manpower
  7. Operators owning responsibility of cleaning own machines / work stations etc

Success Story 4 :-

A Leading Switch & Socket Manufacturing Unit

Project was deployment of Lean concept increased productivity, quality and customer satisfaction.
Project Duration: 6 Months
Results achieved were:
  1. Clean, tidy & a Visual Factory
  2. Set-up time reduction in Molding Shop by 60%
  3. Increase of Productivity by 40-60% for different product assembly lines
  4. Sharp reduction in Customer Complaints
  5. Creation of a World-class Lab
  6. Rearranging RM & FG Stores with FIFO and Quantity Control
Typical activities taken up were:
  1. Cycle Time study & improvement
  2. Adoption of Rabbit Chase concept in Assembly Lines
  3. Rationalizing work contents of operators for better utilization
  4. Creation of Standard Works and up-gradation of work Stations incorporating 2- Bin System
  5. Material feeding frequently @ one hour by Water Spider
  6. Improvement in packaging of outsourced items to facilitate direct material feeding
  7. Employing concept of 3- Fixed in Stores including adoption of FIFO Tags & Quantity Control System
  8. Streamlining Packaging & Dispatch process etc

Success Story 5 :-

A corporate office of a leading Group of Industries

Project was establishing World-class 5S. Time Period: 3-Months

Result of the drive was: A clean, Tidy & Shining Office with basic concept of “A place for everything and everything at its place.”

Areas covered were all offices, IT Room and canteen.

Success Story 6 :-

A Bus Body Building Shop of a leading Automobile Company

Project was to implement Lean Concept in Manufacturing Line and achieving World-class features including improvement in Warehousing system.
Project Duration: 9 Months

Key objectives were to improve 5S Level beyond 70%, Quality Level by 30% or more, reduce inventories and create safe Work Environment avoiding any accidents.

Typical Results achieved were:
  1. 5S Level improved from 47% to 72%
  2. Quality Level improved from 900 DMP to 430 DMP
  3. Inventories reduced from Rs. 25 Cr. to Rs. 13 Cr
  4. zero accidents from original level of 2 accidents per month on an average
  5. much space savings
  6. Implementation of 268 nos. of Kaizens
  7. Organized Stores with built-in FIFO etc
Basic activities taken up were:


  1. Controlled material supplies to Work Stations Bus-wise
  2. Introduction of special material handling trolleys with innovative approach
  3. Creation of special FIFO racks, Bins etc
  4. Reorganization of Work Stations
  5. Numerous safety measures concerning Welding & other critical processes
  6. Better Tool Keeping
  7. Efficient deployment 3- Fixed in Stores all over
  8. Process Improvements for better / reliable Quality
  9. Visual Control all over etc

Success Story 7 :-

An Electrical Wire & Cable Unit

Project was about implementing basic 5S Culture, Reorganizing Stores and reducing wastes in manufacturing shop for increased cost competitiveness by deploying Lean Principles.
Project Duration: 6-months
Results achieved were:
  1. Clean, tidy and Visual Shop
  2. 25% reduction in direct manpower
  3. 40% increase in productivity
  4. 25%-30% reduction in WIP inventories
  5. ease of storage and material handling
Activities taken up were:
  1. Removal of excess machines, materials, work tables etc
  2. Relocating of some of the machines and work stations
  3. Organizing storage of WIP’s defining norms
  4. Relaying out of FG Stores with built-in FIFO system
  5. Deployment of Water Spider System for material feeding
  6. Adoption of proper 5S & Visual control for materials, tools etc

Success Story 8 :-

An After-Market Warehouse of a leading Automobile Company

Project was to make the huge warehouse organized, improving productivity of UC operation and Reducing Bin Denials by 50% or more.
Project Duration: 6 Months

Over and above, the objective was to make space and accountability for New Parts and creation of SOP’s to track KPI’s.

Typical results which could be achieved were:
  1. Reorganization of Interior Stores of about 50,000 parts and packaging materials
  2. Root cause analysis and onset of Productivity Improvement in UC
  3. Root cause analysis and reduction of Bin Denials by about 50%
  4. Creating space and arrangements for proper storage and accounting of New Parts
  5. Creation of critical SOP’s etc

Basic activities taken up were 5S, 3-Fixed & Visual Control, Introduction of 2-Bin Concept, Flow Production system, FIFO etc., innovation in storage practices, planning & monitoring activities etc


Success Story 9 :-

A Warehouse in a leading Automobile Company

Project was to organize warehouses with concepts 3-Fixed and Visual Control in the Chassis and Engine Shops with stocks in excess of Rs. 250 Cr. The ultimate objective was to make better management of inventories and its gradual reduction.
Project Duration: 6 Months
Typical results were:
  1. Organized Stores with 5S & Visual Control in place
  2. Disposing off of Non-Moving / Dead Stocks to the extent possible
  3. Accounting all cases concerning Excess Inventories and better control of Purchases
  4. Proper Stacking of all items with concept of 3- Fixed
  5. Up-gradation of Racks, Shelves, Bins etc
  6. Safety of Materials thru’ effective use of “USE ME FIRST” Tags apart from better stacking
  7. Pouching for ease of counting, stacking and issue of smaller parts and hardware’s
  8. Driving improvement of packaging at suppliers’ ends etc

As per latest information, inventories have come down to well below Rs. 200 Crores which means over 20% reduction.

Success Story 10 :-

A Warehouse in a leading Machine Building Company

Project was to organize some rather messy and challenging warehouses with huge varieties of items. Primary aim was to make it possible to find goods promptly for supply to the Assembly and other Shops.
Project Duration: 12 Months

Typical results have been an enviably World-class Storage system with superb 5S, 3-Fixed and Visual Control.



Success Story 11 :-

A Leading Switch & Socket Manufacturing Unit

Project was to upgrade and reorganize warehouse for increased performance avoiding customer complaints about wrong dispatches as a part of Lean deployment.
Results achieved were:
  1. Clean, tidy & a Visual Warehouse
  2. In-built FIFO
  3. Increase of Productivity by 40-60%
  4. Sharp reduction in Customer Complaints
  5. Implementation of Quantity Control for effective Inventory Management
Typical activities taken up were:
  1. Cycle Time study & improvement
  2. Rationalizing work contents of operators for better utilization
  3. Material feeding frequently @ one hour by Water Spider
  4. Hourly feeding of materials deploying Water Spider
  5. Improvement in packaging of outsourced items to facilitate direct material feeding
  6. Employing concept of 3-Fixed in Stores including adoption of FIFO Tags & Quantity Control System
  7. Avoiding wastes in material feeding by adopting direct feeding instead of multiple material handling
  8. Streamlining Packaging & Dispatch process etc

Success Story 12 :-

A Well-known Mobile Battery Manufacturing Unit

Objectives were:
  1. To make a model flow production line with rabbit-chase concept
  2. To increase productivity by 30-50%
  3. To reduce quality problems by 30-40%
  4. To minimize WIP inventories
  5. To achieve top-class 5S & Visual Control
  6. To save space by 20-30%

Achievements were implementation of model flow line, excellent 5S & Visual Control, more than 100% increase in productivity, reduction in rejections & reworks by 50%, reduction of WIP inventories from 10 hours to 1-hour, and savings in space by 50%.

Additional achievements were:
  1. creation of BOM, Control Plans and SOP’s
  2. training of people on quality and lean tools and techniques

Success Story 13 :-

A Leading Electrical / Home Appliance Unit

Project was to help establish a Ceiling Fan Manufacturing set up with Lean Concept—from concept to commissioning. Typical deliverables were:
  1. Overall Inventories of less than 10 days
  2. Half the Space Occupied
  3. World-class material handling and storage system, etc. All these are over comparable Indian Industries